Problem:
As part of Brexit mitigation as well as compliance, our client needed to apply for Private Customs Warehouse status on behalf of a manufacturer who had various off-site storage locations.
Solution:
VernonRato collected all of the information from various applications, which as the company was not accredited with AEO, happened to be four different applications, as well as reapplying for CCG (Customs Comprehensive Guarantee). IT interfacing with the CMS (Customs Management System), inventory management, SAP (Systems, Applications and Products) and freight forwarder interfaces all fell within the scope of the project.
Results:
The project was successfully completed in 3 months as well as the audit taking place during month 4. The company received their Customs Warehouse authorisation within 5 months of the start of the project.
£100 million duty savings
Costs Saved
5 Months
Time Taken